Heathrow blames CAA for third runway delay

Government
James Chapple
20 December 2019

Plans to expand Heathrow by creation of a third runway could be delayed by up to three years, the airport has confirmed.

Heathrow's third runway is now in doubt

Heathrow says the CAA’s consultation on pre-expansion “early Category C costs” would delay its expansion timetable “by at least 12 months”.


The airport had hoped to have the new runway operational by 2026, but now expects to complete the work “between early 2028 and late 2029”.


It comes after the CAA rejected Heathrow’s call to nearly quadruple spending on the project from £650 million to upwards of £2.4 billion before it has even gained planning permission for expansion.


The regulator’s concern is that id costs soar and Heathrow is subsequently denied permission to pursue expansion, passengers could end up footing the bill.